Solar Power Plant Sample Project Details

Turkey’s Solar Energy Potential and Unlicensed Solar Power Plant Projects

Türkiye has an enormous solar energy potential due to its geographical location. According to the Solar Energy Potential Atlas, the annual sunshine duration in our country is 2,737 hours and the total annual solar energy is 1,527 kWh/m².year. This potential is seen more efficiently, especially in the southern regions.

Considering the projected costs for an unlicensed megawatt solar power plant project, a detailed plan is required for the equipment to be installed and the required space. For example, for a 1 MW power plant, equipment such as approximately 4,000 260/265 Watt solar panels, aluminum construction mounting systems, inverters, and remote monitoring systems are required. In addition, elements such as land preparation, landscaping and security systems should also be taken into consideration.

MaterialAmount
Solar Panel4.000 adet
Alüminyum Konstrüksiyon SistemleriBelirtilmemiş
İnvertör25 KW, 40 adet
Uzaktan İzleme SistemiBelirtilmemiş
Solar Kablo ve BağlantılarBelirtilmemiş
Trifaze Çift Yönlü Elektrik Sayacı1 adet
ParatonerBelirtilmemiş
Çit, Hafriyat, İnşaatBelirtilmemiş
Arazi Gereksinimi21.000m²
Proje İçeriğiMiktar/adet
Solar PV Panel4.000 Adet
25 KW İnverter40 Adet
Kontrol ve İzleme Sistemi4 Adet
Sabit Montaj Yapısı1 Set
DC Kablolama21.000 Metre
Toplama Panosu1 Set
Çit ve Kapı İşlemleri1.000 m²
Peysaj ve Toprak İşleri1.500 m³
Yıldırımdan Korunma Sistemleri1 Set
Video Güvenlik Sistemleri1 Set
Trafo, Köşk, Hücreler, ENH İşleri1 Set
İşçilik1 Set
AC Kablolama3.750 Metre

Regional evaluation of projects is important. For example, if a 1 MW solar power plant is established in a region with high solar potential such as Mersin, monthly and annual electricity production can be estimated. In this planning, the economic return of the investment should also be taken into account. The state’s energy purchase guarantee and incentives offer investors a profitable perspective in the long term.

However, when calculating costs and returns, the advantages of domestic production and the impact of national regulations should not be ignored. Particularly in unlicensed solar energy projects, encouraging local production and providing support in this direction plays an important role.

This information can serve as a guide for those who want to invest in solar energy. A balanced evaluation of geographical location, costs and returns of the project can form the key elements for a successful solar energy project.

BölgeGüneşlenme Süresi (saat/yıl)Gelen Güneş Enerjisi (kWh/m².yıl)
Güneydoğu Anadolu30001.460
Akdeniz2.956
Doğu Anadolu2.664
İç Anadolu2.628
Ege Bölgesi2.738
Marmara2.409
Karadeniz1.9711.120

Mersin İli Güneş Enerjisi Verileri

AylarKurulu kWhÖngörülen kWhÜretilen kW%90 Performans*
Ocak1.000617,4093.783,0684.404
Şubat1.000620,50100.421,7290.379
Mart1.000632,50140.389,70126.350
Aralık1.000627,5085.591,0077.031
TOPLAM1.000665,602.023.411,591.821.070

Maliyet ve Getiri Hesaplamaları

AylarYerli Modül Teşvikli Getiri ($)Yerli Modül Olmaksızın Getiri ($)
Ocak12.99811.225
Şubat13.91812.020
Mart19.45816.804
Aralık11.86210.245
TOPLAM280.444242.202